当前位置:首页 >> 其它语言学习 >>

2011 Transformer PD monitoring case study


Transformer PD Monitoring Case Study
Richard Heywood Matthias Boltze Sacha Markalous Carl Johnstone

Doble PowerTest Ltd, UK bl d

Introduction Because of … ? Increasing age of in-service power transformers f f ? Increasing need for utilities to maximise use of transformers while maintaining system reliability. reliability ? Increasing forced outage costs Condition monitoring and life cycle management of power transformers have received considerable attention, with many new monitoring techniques available, especially it i t h i il bl i ll for partial discharge fault detection and localization. Difficult to decide when to introduce monitoring on a power transformer and how to use monitoring to assist in asset management, particularly for suspect units. g ,p y p
2

Background This story started in late 2008… ?400/275/13kV 750 MVA auto-transformer (no tap changer) p ?Important location in London network ?28 years service ?LV cable through-fault on the attached circuit – may have g y contributed to the failure of a Quad Booster at the other end of the 275kV circuit ?Online PD monitoring system on 400 kV GIS system detected an increase in PD activity on the gas zone connected to this transformer. transformer Concern about the condition of the transformer and the reliability of the circuit. circuit
3

The transformer

4

Step 1: Enhanced DGA sampling DGA i invented i the UK t d in th Over the years many power transformers have been saved by effective DGA analysis therefore Enhanced oil sampling was first decided to check if there as was any indication of possibly developing fault inside the transformer. transformer

5

Step 1: Enhanced DGA sampling
Significant increase in hydrogen and acetylene in main tank 60

H2
50

C2H2

Gas concentratio (ppm) on

40

30

20

10

0 12/06/2007 08/11/2007 Sample date 21/01/2009 06/02/2009

Significant increase in acetylene to 26ppm from trace, and the resample not only confirmed the high level of acetylene but also showed a further increase to 30ppm within two weeks. Such a DGA signature is typical of an arcing/sparking fault in the main tank of a power transformer. It was then decided to carry out PD measurements to investigate further. y g
6

Step 2:GIS PD monitoring

PD activity appeared to be on the Yellow phase of the transformer. p
7

Step 2: Neutral RF CT measurements

8

Step 3: Review of design, history and DGA

AE PD location in a sister transformer in December 1990
9

Step 3: Review of design, history and DGA

Photo from 2001 inspection showing carbon p g marks around loose clamping screws
10

Gas concent tration (ppm)
100 150 200 250 50 0

24/01/1985 26/06/1985 27/11/1985 18/03/1986 24/09/1986 29/12/1986 20/02/1989 06/12/1990 25/10/1991 20/07/1995 21/04/1997 02/12/1999 04/03/2001 26/03/2001 17/04/2001 16/11/2001 13/06/2002 19/07/2004 12/08/2004 22/09/2004 15/02/2005
Sample date

H2

Step 3: Review of design, history and DGA

31/01/2006 31/05/2007 21/01/2009

History of diagnostic hydrogen and acetylene in main tank of transformer T6607

C2H2

19/03/2009 17/04/2009 11/06/2009

11

Step 3: Review of design, history and DGA
History of combustible gases in main tank of transformer T6607
100 90 80 70 60 50 40 30 20 10 0 13/04/2000 11/01/2001 09/04/2001 02/10/2001 21/01/2009 06/02/2009 04/03/2009

%CO

%H2

%CH4

%C2H4

%C2H6

%C2H2

Conclusion was that most likely some of the clamping bolts were loose again after they had been retightened in 2001.
12

Step 4: Winding movement assessment

Clearly more in-depth investigation required. Outage scheduled for off line testing and internal off-line inspection. In view of the recent 275 kV through-fault it was decided to check mechanical condition by carrying out SFRA measurements before any remedial work carried out to retighten clamping bolts.

13

Step 4: SFRA test
10 0 -10 -20 -30 -40
-20 0 -10

HV to LV

A m p litu d e in d B

LV to N

-50 -60 -70 -80 0 50000 100000 150000

-30 30 A m p litu d e in d B -40 -50 -60 -70 -80

200000

Frequency in Hz

No evidence of winding g movement, so can re-clamp.

-90 -100 0 50000 100000 150000

2

Frequency in Hz

14

Step 5: Internal inspection and repair p p p

Photo from internal inspection on the critical transformer in 2007, 2007 B (Yellow) phase HV side clamping bolts
15

Step 6: On-line UHF PD measurement
In order to confirm the effectiveness of the repair, it was then decided to use on-line UHF PD measurements when transformer back to service to ensure it was discharge free.

Doble Lemke PD Measuring System LDS-6/UHF

16

Step 6: On-line UHF PD measurements

UHF drain valve sensor (left) and LDS-6/UHF measuring system (right)
17

UHF PD probe measurements

Only low-level PD activity measured !
18

Postscript:

After return to service following repair the acetylene level in main tank fell to trace (l i t k f ll t t (less than 3 ppm), confirming the th ) fi i th success of re-clamping. Nevertheless, it was decided that the transformer should remain at Condition Category 4 (normal) in the Transformer Asset Health Review, but with periodic on-line GIS PD monitoring and regular routine oil DGA sampling to monitor its condition – and RFI surveys. surveys

19

On-line UHF RFI surveys

20

PDS100
? Scan the site in seconds ? D t t PD at an early stage Detect t l t ? Record PD activity

Non-invasive method Hand held, battery operated, easy to use RF CT and TEV sensors now available

- Doble PDS100 -

21

PD-Smart
Input Unit vPD
PD-Signal g
A D

DAQ

DSP
Filtering Detection

PC

Postprocessing

vU
Voltage Signal
A D

?P

Computer Software User/ Panel

22

PD alternatives ?‘Conventional’ IEC 60270 ?Acoustic i ?UHF ?RFI
Requires direct electrical coupling

Effective for location of ‘shallow’ faults

Most sensitive

Most convenient, very effective
23

Conclusions and Recommendations
?Step-by-step approach use of monitoring/diagnostics recommended to assist management of suspect units ?Monitoring should target suspected fault Monitoring ?Knowledge of design weaknesses and likely failure modes Knowledge invaluable in directing investigation ?Objective is proactive use of monitoring/diagnostics to prevent unplanned outage or catastrophic failure.

24


相关文章:
2011 Transformer PD monitoring case study_图文.pdf
2011 Transformer PD monitoring case study_其它语言学习_外语学习_教育专区。...Objective is proactive use of monitoring/diagnostics to prevent unplanned ...
PD_2_PD_Testing_and_Monitoring_of_Transformers.pdf
PD_2_PD_Testing_and_Monitoring_of_Transformers_...UHF transformer probes applied through oilvalves in...PD decoupling (in particular in case of ...
...for improved interpertation of pd measurements_图文.pdf
The transformer was excited via the 10 kV ...4 3 CASE STUDY ON PD LOCALIZATION WITH COMBINED...line monitoring is only useful to a limited ...
Online_PD_Monitoring_Power_Cables.pdf
Online_PD_Monitoring_Power_Cables_互联网_IT/...transformer sealing ends, cable terminations for ...Case Study 1: AC- and PD- Commissioning Test ...
2011FME转换器快速参考手册-中文版_图文.pdf
2011FME转换器快速参考手册-中文版_IT/计算机_专业...(Manipulators 类别), 18 C CaseChanger (Strings ...(Manipulators 类别), 20 CustomTransformerLooper (...
2011美国创新事业规划研修团分享_图文.pdf
2011美国创新事业规划研修团分享_经管营销_专业资料。PD F -X C h a n ge...( Business Model Innovation Workshop 9:00am~4:30pm Day1 Case Study with...
Condition Monitoring and Diagnosis of POWER TRANSFORMERS.pdf
Condition Monitoring and Diagnosis of POWER ...In most cases they cannot work alone to solve ...PD pulses within the transformer by mathematical ...
Rule 21 Working Group Workshop Notes 29 April 2011.pdf
PG&E Case Study: Volume and Complexity of Net Energy Metering Interconnection...(per customer or per transformer); and (2) other conservative technical ...
俞云松 非发酵菌相关感染现状及治疗(2011)_图文.ppt
Study Retrospective matched cohort study Retrospective matched casecontrol study ...(不产生ESBLs) 头孢哌酮/舒巴坦对产ESBLs菌株MIC分布 PK/PD参数模拟(头孢哌...
大型电动机_电机のオンライン断技术_图文.pdf
Transformer Wedge Void U D d Cupper 5 10 15 ... Case study of partial discharge inception ... 300 nm PD sensor on rotating machines ICEMS2006...
...Balance Type of Optical Fiber Current Transformer.pdf
Study on Magneto-Optic Balance Type of Optical Fiber Current Transformer 2011 Third International Conference on Measuring Technology and Mechatronics Automation ...
MATLAB 7.12.0 (R2011a) - Saturable Transformer with ....pdf
MATLAB 7.12.0 (R2011a) - Saturable Transformer with Hysteresis_电子/电路_工程科技_专业资料。power_transfohyst.mdl Open this model Saturable Transformer ...
转换器IC AP3983BCD 英文规格书.pdf
Fully EU Directive 2002/95/EC (RoHS) & 2011/..., 1%, 1206 EE20 core, PC40, transformer ...PD Total Power Dissipation W Note 5: Stresses ...
RTLab培训资料_OP104_Module5_图文.pdf
(DC link of the drive, or the transformer winding are sometimes the good... 10/25/2011 Case Study: HVDC system with switched AC filter banks Memory...
A transformer model for winding fault studies_图文.pdf
In the case of a three-phase transformer with two windings, these matrices... Base for the Study of Protection and Monitoring Systems" 1 2 t h ...
PSCAD的继电保护部分Protection_图文.ppt
Transformer differential protection ? July 19, 2011 Case Study - Capacitor Bank Switching Transients Page 11 The Design Problem Problem relating to the ...
RS232RS485商业级袖珍型接口转换器UT-2011说明书.pdf
RS232RS485商业级袖珍型接口转换器UT-2011说明书_信息与通信_工程
...study of adsorbate ordering at atomic steps of Pd.doc
ordering at atomic steps of Pd_英语_高中教育_... March 2011, Purchase Pages 290-293 $ 31.50 ... A case study of furniture and decoration ...
基于GIS空间分析的变电站空间布局规划研究_以北京为例.pdf
TRANSFORMER SUBSTATION BASED ON GIS ANALYSIS: A CASE STUDY ON BEIJING 魏...126 2011年 第35卷 增刊1 VOL.35 SUPPLEMENT Ⅰ 2011 图2 220kV变电站空间...
PD69104B datasheet.pdf
Continuous monitoring port and system data ? ...CASE 4° -10 to +85 Note: Available in Tape...PD69104B Copyright ? 2011 Microsemi Rev. 1.3 ...