Risk management and mitigation strategies in the supply chain


Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.
Dafne Sacchi Homrich*, Maria Inácia Favila Salum*, Ant?nio Sérgio Coelho*, Carlos M. Taboada Rodriguez*
Production and Systems Department, School of Engineering, Federal University of Santa Catarina, Campus of Trindade, 88040-970 Florianópolis, Brasil Email: dafnesh@gmail.com, mariainaciafavila@gmail.com, coelho@deps.ufsc.br, taboada@gmail.com
*

Abstract During the evolutionary process of the organizations, competitiveness became a preponderant factor, making each and every organizational initiative to be directed towards creating a differential that increases their competitiveness. The insertion and integration process of economies in international trade – more and more globalized - is fundamental for the economic growth strategy. There is a perceived tendency for international integration of the supply chain (SC), however, the greater it is global expansion the greater it is the likelihood of uncertainties and accidents – by disturbing on one of the chain links - affecting other parts of the chain. In the past years it has been widely discussed the concept of Supply Chain Risk Management (SCRM), tool that assists on the implementation of actions aimed at managing potential risks management, and actions aimed at minimizing the impact of external risks to ensure greater reliability throughout the supply chain. In this sense, the objective of this study is to provide empirical information of the risk management implementing process within an aeronautical industry supply chain. Keywords: Supply chain; risk management, empirical research, SCRM implementation.

1

Introduction

In the current economic environment it is emphasized that the competition is shifting from a relationship between competing companies to a relationship between different organizational arrangements, among which the supply chain is highlighted. The notion of supply chain management (SCM) is a concept that has evolved in recent decades rising from the evolutionary movement that came of business logistics. Notably, the growing concern in managing the supply chain is partly due to two major groups: on one hand, companies seeking to concentrate on core competencies and reduce costs, have begun to outsource major parts of their production to other companies other regions or countries, requiring a robust logistics management. On the other hand, the turbulence and chaos in the competitive environment triggered by environmental, political, socioeconomic, and other factors, that require businesses adaptation, flexibility and quick responses ahead to market changes often unpredictable. Therefore, it becomes clear that after a period of production systems fragmentation seeking to reduce costs and focusing on core competencies, companies are faced with ruptures risks among the various links, from suppliers, transport, production, distribution to retail and consumer. The supply chain "in their simplest degree of complexity consists of three entities: the company, a supplier and a customer directly involved in upstream and downstream flows of products, services, finance and information", according to Jüttner (2005, p . 121). In this context, supply chain management "encompasses all stages involved" inside and within these companies in order to meet client expectations (CHOPRA & MEINDL, 2003, p. 3). The issue of disruptions risk in the companies supply chain around the world has been the subject of recent studies, as companies are connected in global supply chains there is a real vulnerability condition in the operations flow. Following Jüttner, Peck and Christopher (2003, p. 3) "a disruption that affects an entity anywhere in the supply chain can have a direct effect on the ability of another company to continue operations [...]." The point is that is not enough for each link to worry about their risk management to

ID341.1

ICIEOM 2012 - Guimar?es, Portugal

solve problems because, in the context of supply chain exposures, risk management requires solutions involving the entire chain.

2

Methodology

The theme of risks is not new but has been progressively more exploited in the field of supply chain management (LAVASTRE ET AL., 2012), consequently the demand for studies and results in the area is increasing. Khan and Burnes (2007) emphasize that research on SCRM need (a) be within a larger study on risk, yet, (b) require wider and deeper empirical research, and (c) need to develop well-founded models of SCRM . Also, recently, Christopher et al. (2011) pointed to future research that might (d) consider the input suppliers and logistics service providers involved, and (e) the formation of multi-research groups looking at different perspectives of risk for SC globally. After this, the purpose of this study can be justified as a way to contribute to the growth of empirical material in the area of SCRM. The main steps followed to implement the Risk Management were: To analyze existing methodologies for Risk Management already performed by other departments in the company (Pros x Cons), to define and initiate a risk management methodology for the management of Logistics and Transport with the teams responsible for controlling and enforcing contracts,; Dissemination and Release of the methodology for all stakeholders; Performing workshops in each of the national units with their respective stakeholders; analyze results of the workshops; Building up an Action Plan; Restitution to responsible for risk mitigation and continuous monitoring. When structuring in one organized way the steps that make up the realization of a job or task, including its flow, inputs, activities and products generated, it is often possible to obtain systematic information and understand critical points, opportunities for improvement and especially the variations or fluctuations due to normal causes (intrinsic to the nature of the process) or due to abnormal or specific causes. In short, the aim was to develop processes capable of ensuring activities harmonization as well as the information flow for all national units. One of the main characteristics of this mission was to make it simple; consequently these processes should be easily understood and utilized by all users.

3

Literature Review

3.1 Risk Management
In the supply chain many can be the sources of risk, since different parts of the chain will be exposed to different hazards. In addition, organizations, in order to become more agile and lean, are becoming more dependent on external agents, which also contributes to greater overall vulnerability (FAISAL ET AL., 2006). A survey performed by Aon Corporation, in 2009, with business leaders from over 40 countries, including 551 companies, raised a list of the top 10 most important risks in these participating organizations. The research clearly shows that a crisis impacting the global economy was identified as the most important risk in their organizations. Other major risks cited include compliance with regulatory standards, business disruption, face the challenges of increased competition, commodities price risk, protecting the reputation, managing risks associated with cash flow, supply chains, dependence on third parties and recruit and retain talented individuals. Each of these risks has increased in scale and complexity, given the state of the current economic environment. According to Christopher (2009), it is important to identify the risk profile of a business, because from that profile you can find "critical paths" within a network. This profile aims to find the main vulnerabilities and establish what is the probability of business disruption. Thereby, the author classifies the main sources of risk on the network as: supply risk, these risks are related to the flow of products, services and information that arise between the supplier and the enterprise, related to the supply chain before the production or operation. Ex: acquisition of global products,
ID341.2

Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.

dependence on suppliers, poor management of supplies, etc. Concomitantly, demand risk is related to the flow of products, services and information that arise between the company and the consumer market. Ex: Volatility of demand, bullwhip effect. Process risks are related to the way organizations produce goods or services, beginning by obtaining raw materials, through processing, until the delivery of finished products. Ex: Identifying bottlenecks in manufacturing, availability of additional production capacity etc. Another important source of risk is the control of monitor, standards, procedures and policies systems that manage how the company exercises control over the process. Ex: disorder and distortions caused by inappropriate internal control of their own systems such as, request opportunity, lot sizing and safety stock policy away from the real demand. At last, there is environmental risk linked with the external environment of the supply network and not controlled by the organization, such as regulatory changes, socio-political, macroeconomic and natural or manmade disasters. Although the type and timing of these events cannot be predicted, its impact must be evaluated. The efficient coordination of the supply chain is directly related to the company's ability to achieve competitive advantage. The flow of goods and services must be integrated from the beginning to the end of the chain in order to contribute to customer satisfaction. (Cousins and Spekman, 2003). The leaner and more integrated supply chains get the greater is the likelihood of uncertainties, dynamics and accidents in one link affect other links in the chain(FAISAL, BANWET ET AL., 2006). Risk management is the identification, assessment and prioritization of risks followed by coordinated and economic resources application to minimize, monitor and control the likelihood and / or the impact of intrusive events. Manage the SC risks becomes an important tool to add value to the market and it’s also a more proactive way for companies to avoid disruptions throughout its supply chain. The risk management process is focused on understanding risks, minimizing their impact by using, for example, probability and direct consequences. Generally, companies act on recurrent and low impact risks on their SC, and have a propensity to ignore those with high impact and low probability of occurrence. But it is important to be careful, because disasters, as recently observed in Japan, natural or even manmade, had a low probability of occurrence, but ended up causing major damage. Thus, it is necessary to rethink the approaches to SCRM, since, due to globalization, companies appear to depend on partners from different nations and continents.

3.2 Mitigation Strategies
Incidents of risk and disruption in the value chain occur continuously in globalized supply chain. Still, it is possible to say that currently there are several facilitators that help mitigate (attenuate) risks in the SC. There are many risks and approaches to mitigate risks to consider, but two things are important when starting building a strategy SCRM. First, you must create an understanding throughout the organization about the risks that are in SC. Next, determine how to adapt a generalized approach to mitigating risks to the circumstances of a particular company. (Chopra and Sodhi, 2004) Faisal, Banwet et al. (2006), presented a compilation of some factors that act as facilitators in mitigating the risks related to the supply chain, following the ideas proposed by some other authors on the literature, they are: (a) Information sharing - Increasing the visibility of demand information across supply chain reduces the risks (Chopra and Sodhi, 2004). Thus, communication and coordination among all elements of the supply chain are essential to its success. (b) Agility in the supply chain defined as the ability to thrive in a continuously changing, unpredictable business environment (Prater et al., 2001). Companies can minimize inventory risks by working with a highly responsive supplier (Chopra and Sodhi, 2004). (c) Trust among supply chain partners expectation that partners will not act in an opportunistic manner even if there are short-term incentives to do so and can contribute significantly to the long-term stability of an organization and its supply chain (Spekman et al., 1998). (d) Collaborative relationships among supply chain partners - In order to manage risk effectively in a supply chain, organizations are moving to adopt closer relationships with key suppliers. (e) Information security, the goal of security is to

ID341.3

ICIEOM 2012 - Guimar?es, Portugal

reduce the enterprise’s risk of losses caused by intrusion, system misuse, privilege abuse, tampering, fraud, etc. Protection must be provided against external threats and from internal abuse. Other factors equally relevant are: (f) Corporate social responsibility - Socially responsible companies consider the full scope of their impact on communities and the environment when making decisions, balancing the needs of stakeholders with their need to make a profit. (g) Aligning incentives and revenue sharing policies in a supply chain, induce supply chain partners to behave in ways that are best for everybody, companies have to create or modify monetary incentives. A supply chain works well if the incentives of its member companies are aligned which requires the risks, costs, and rewards of doing business are distributed fairly across the network. (h) Strategic risk planning - companies that will be successful are those that can identify and develop contingency plans for the various risks that exist internally and externally to the organization. Formulating an appropriate and effective organizational strategy can to a certain extent mitigate supply chain risks (Finch, 2004). (i) Risk sharing in a supply chain the company must identify not only direct risks to its operations, but also the potential causes or sources of those risks at every significant link along the supply chain (Christopher et al.,2002). (j) Knowledge about risks in a supply chain – By understanding the variety and interconnectedness of supply-chain risks, managers make better decisions and can tailor balanced, effective risk-reduction strategies for their companies, which may decreases the risks of both a single organization and a whole network. (Chopra and Sodhi, 2004). At last, (k) Continual risk analysis and assessment, continual monitoring of risks assumes importance because business environments in which supply chains works are very dynamic, and risks to a supply chain may change due to changes in the political/economic conditions of the environment, mergers/acquisitions, etc.

4

Case study in the aeronautical industry

This company launched a 4 years corporative project, started on 2007. It was a turnaround program that had been developed consisting in the implementation of a new business model, continuous improvement and reduction of cash exposure. Therefore, mid-2007, the department decided to restructure the operations of two major manufacturing support functions, "Manufacturing Engineering" and "Supply Chain & Logistics". In this context, for the Supply chain and Logistics department, one of the Key projects was to develop an integrated European approach to company’s Logistics based on 4PL/3PL model, the goal was to end the multitude of existing contracts with current providers by implementing this new concept of a European single provider. This would therefore allow company to achieve its rationalization objectives, involving in particular the establishment of regional hubs, warehouse automation, more efficient logistics solutions, etc. eliminating activities that didn’t add any value and were expensive for the company Therefore two main companies had been selected as lead logistics and transport providers (“Lead Logistics Provider - LLP” and “Lead Transport Provider - LTP”, respectively) for state of the art companywide solutions and to secure planned savings, maintaining or increasing the level and quality control throughout their supply chain. Within the operational function of Central Supply Chain, together with local logistics services managers in Europe (LSM), it was begun to collect and analyze the requirements in terms of risk analysis (for contract management LLP / LTP), propose and implement a risk management process in correspondence with the internal audit resulting in a convenient way to carry out the operations. The following illustration (figure 1) shows one way to interpret risk management in a time scale.

ID341.4

Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.

Figure 1: Risk management in a time scale. Source: Company’s internal documentation 2009.

After analysis of existing methodologies for risk management, considering its pros and cons, the tool FMEA - Failure Mode and Effects Analysis - was considered the most suitable to be implemented in the Logistics and Transport operations department. The FMEA can be described as a systematic group of activities designed to: ? ? ? Recognize and evaluate potential failures of a product or process and the effects of that failure. Identify actions that could eliminate or reduce the chance of occurrence of potential failure Document the process.

In FMEA, failures are prioritized according to how serious their consequences are, how frequently they occur and how easily they can be detected. The purpose of the FMEA is to evaluate risk management priorities for mitigating known threat vulnerabilities, starting with the highest-priority ones. As for the Operational Logistic / Transportation management, the following illustration (figure 2) describes basically the necessary loop to perform the risk management. Later, on table 1, this circle will be explained item by item.

?
Figure 2: Operational Logistic / Transportation loop. Source: Company’s internal documentation 2009. ID341.5

ICIEOM 2012 - Guimar?es, Portugal

Table 1: Process description Process Activity What Who

“Process Mapping” review. Analyze if the Process defined by logistics department is applicable and correspondent to real life activities (Make sure it contains all process and sub-process to be analyzed further on) 1 Identify process PS: Where particular business needs or departmental operating methods necessitate changes to detail these processes, these changes are acceptable. All comments and suggestions to improvements must be addressed to the process owner. Classify by order of Criticity all the pre-defined activity sub-processes 2 Most critical (Critical Priority to be analyzed mandatory for risk assessment; the ones Activity/Process classified as High Priority are to be discussed, between team members, if a risk assessment analysis is necessary.) Identification of all the risks per sub process (Brain Storming). Definition 3 Most critical of Severity of effect, likehood of occurrence, detection control and Risk/Failure per Security, quality, cost, delivery, people (SQCDP) risks impact assessment. activity Risk assessment decides which risks the project must pay attention to and allocate resources to manage Identification of likely the root causes by using for example the 5M Methodology (The ?5M? method permits not to forget any constituent during the studied activity analysis.) either 5 why Methodology. (Analysis 4 Root causes and Brainstorming based on company’s organization & processes , analysis/risk internal service level agreements, current rules and practices either (Ishikawa) LLP/LTP organizations and contractual agreements) Root causes will help to find appropriate Risk owner and to establish the adequate action for risk mitigation. Define contingency and mitigation action plan for most critical risks 5 Prioritised Action previously identified and assessed taking in account the root causes raised previously. Plan One action defined may be applied to one or several different risks when identified root causes are equal. Communicate, present the Workshop conclusions and mitigation plan to 6 TMTL Risks owner in order to confirm, develop and launch the actions Management Plan highlighted during the risk management workshop. Follow up the action Plan (actions status and results) Source: Company’s internal documentation 2009.

Lean & Organisation Manager

Team members by common sense and business feedback experience (Team Member by Lean & Organisation Manager)

Lean & Organization Manager

The methodology adopted to be performed during the ‘workshops’ with the stakeholders embraced some key elements for it to work properly, such as: Anticipation Approach - to avoid Business disruption and potential impacts for Customers, Aircraft deliveries ,safety, non quality, extra costs; Based on their feedback and experience on Day by Day Business Management, meaning that it should not be considered as a theoretical exercise; Closely linked to business performance monitoring; Participative way of working; Accessorized by a Quality specialist on risk management, who would drive the risk management methodology; Step by step and Continuous approach - Risks identification and assessment based on criticity (quarterly) and risk mitigation plan review (monthly). After mapping the process to be analyzed, each step of this process must then be evaluated to create activities prioritization subsequent to the needs of assessment in relation to risks rising. This prioritization is done following three arguments represented in binary way: impact, ease of identification / recognition and urgency, as shown on table 2.

ID341.6

Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.

Table 2 – Prioritization Arguments Importance of the part / process Minor impact on production or business 0 Moderate Importance Not critical to safety No affect to external customers Directly affects aircraft performance or safety Directly impacts a long lead-time or high-cost item Could cause severe production or business disruption 1 High importance A potentially serious hazard to personnel New design, material or process. Unknown capability A feature with known problems EASE Difficulty of analysis Lack of adequate information availability 0 High Resistance The right people and skills are not accessible Lack of management support / focus Adequate information / data is available 1 Low Resistance The required people and skills are available A good level of support / focus from the local management teams URGENCY Time constraints No immediate concern to productivity, safety, quality 0 Non urgent Not a current threat to the programme Customer not affected by delay Immediate concern to productivity, safety or quality A current threat to the programme 1 Urgent A customer is impacted Source: Company’s internal documentation 2009. IMPACT

As a result of this assessment, the sub processes will be classified as Critical if the sum is equal to 3; High if the sum is equal to 2; Moderate if the sum is equal to 1 or Low if the sum is equal to 0. The Risk identification step can be considered as the most important step in risk management - risks that are not identified cannot be managed. It is also the stage at which people in the unit are most involved. Almost all risk identification involves tapping into the knowledge of people in the unit - they tend to have the most knowledge of the subject, the practical concerns and the organizational issues. The evaluation of each one of the risks, raised by managers, according to their priority is performed based on three items, the severity of the effect, the likelihood of occurrence, detection control, evaluated on a 15 scale, according to the characteristics defined in Figure 3, Figure 4 and Figure 5.

SEV 1 2 3 4 5

Local effects at the Process Manufacturing Operation
Negligible effect on safety, quality, costs, productivity or assets. Slight inconvenient Minor, recoverable impact eg. Concession, rew ork, tool breakdow n, intervention Moderate eg; significant cost / scrap impact, major rew ork, recordable safety event High eg. Major cost / scrap impact. Stopped production. HSE reportable event Severe impact eg. Production Shut dow n, permanent disability

Subsequent Internal Operations
Negligible adverse effect Recoverable impact eg. Delays, repairs Significant (non-recoverable) delays/cost/w ork Major disruption to production or people safety Productio / business disruption

Aircraft End-user / Customer
Negligible customer effect Noticeable but no impact on performance or safety Dissatisfied eg; quality, delay. No safety impact Performance / functional / safety / regulatory failure Loss of market share or regulatory compliance

Figure 3 - Severity of the effect scale. Source: Company’s internal documentation 2009.

ID341.7

ICIEOM 2012 - Guimar?es, Portugal

OCC 1 2 3 4 5 DET 1 2 3 4 5

Process capability
Robust, consistently meets requirements Adequate capability Borderline process capability Poor process capability Unreliable, not capable for manufacture

Failures
Remote very unlikely Infrequent / Rare Occasional Frequent / Regular Persistent : Inevitable

Cpk (fail rate)
>1.3 (1 in 20K) 1.1 (1 in 2000) 0.95 (1 in 500) 0.75 (1 in 100) <0.55 (1 in

Figure 4 - Likelihood of occurrence scale. Source: Company’s internal documentation 2009.

Prevention and Detection Controls
Controls provide early w arning and should allaw the failure to be prevented Failure can sometimes be prevented. If it does occur detection is very likely Failure / defect should be readily detected, but this could be at a later stage Detection is possible but unreliable, some fails / defects remain undetectable Detection difficult or unlikely w ith poor / no controls. Defects reach custome

Detection
Before fail Same op. Subsequent op. Customer In-service

Figure 5 - Detection control scale. Source: Company’s internal documentation 2009.

The previous assessment generates a RPN ("Risk Priority Numbers"), which consists in the multiplication of the three results obtained on each of the items evaluated. The purpose of risk assessment is simple - it is to decide which risks the project must pay attention to and allocate resources to manage; and which risks are lower priorities. Hence, the main risks are classified at intervals of "High to Critical (HC)" when RPN is>= 25 "Medium to High (MH)," RPN <25, but the severity is >= 4. (Figure 6).

Figure 6 – Process flow according to risks RPN. Source: Company’s internal documentation 2009.

As a result for the Operational Risk Management, after performing Workshops with all main stakeholders from Logistics team of every different facility, it was possible to classify many potentials failure mode and propose some action to mitigate those risks. The sheet template below (figure 7) is a summarized result of the Risk Analysis Workshops performed by the department and it was created with the aim of Risk Analysis Manage / control and follow Risks evolution on a global view.

ID341.8

Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.

Logistics Risk Summary Template
Purpose: This Document is a result of the Risk Analysis performed by TMTL. It was created with the aim of Risk Analysis Manage / control and follow Risques evolution on a global view.
?The objective is, to provide a global and detailed overview of the Major Company Risks (‘Top Ten’), that is current, updated and approved by the business area accountable person.

Sort By Criticality 0 1 2 3 4 5 6 7 8 9 10 Risk N°
(Traceability)

Top Ten' Risks Mix between goods and paperwork (right material , wrong paper) Early production order preparation Wrong quantity prepared Late start in issuing the purchase request Missing people with Buy side access to raise Preq (ie : holidays, out of office..) I.T. break down (INTERFACE BETWEEN SAP AND PSI) Wrong handling of hazardous goods Missing documentation for Dangerous Goods Missing of best practice solutions/offers/support No continous improvements

RPN Risk Owner 27 27 27 27 27 5 4 4 4 4

Criticality
Overall Status

Trend Central Risk Management Comments

N° of SQCD items Impacted 3 2 2 1 1 3 5 4 4 4

2.5.1 2.3.4 2.3.1 1.3.5 1.3.1 2.9.1 2.7.3 2.2.5 2.7.4 2.7.5

HC HC HC HC HC MC MC MC MC MC

Figure 7 – List of 'Top ten' major risks. Source: Company’s internal documentation 2009.

These risks can lead to greater dysfunctions and therefore must be handled in a short / medium term. The total risks raised can easily be seen in the figure 8.
N° of Sub Process Total

19
Is s ue PR 2.1 EQ Inb ou 2.2 nd Sto r ag 2.3 e Pr oc es 2.4 s in In g dis te rn tr ib al uti on 2.5 E dis x ter tr ib nal uti on 2.7 Qu em alif plo ica t io ye nL e 2.8 LP On ac tiv i side tie s 2.9 IT Ma 3.4 na ge Va me lid ate nt 3.5 Inv Ma oic Cu n e sto age (S mer Inte LA r r n e la ) a tio l 4.2 n Cr ne e at e& go s p tiate ec te i f ev ica t c hnic olu io al t io n n

Critical Sub Process

1.3

12 56 5 20

N° Total of risks Identified N° of (HC) N° of (MH)
Legend:

7 2 2

5 0 1

6 0 2

4 2 0

6 0 1

7 1 3

6 0 5

3 0 3

1 0 1

2 0 0

5 0 0

4 0 2

High to Critical (HC) Risks: Med to High (MH) Risks:

RPN>= 25 RPN<= 25 but SEV>=4

Low to Medium (LM) Risks: RPN < 25 and SEV < 4

Figure 8 - Amount of risks by its critical activity. Source: Company’s internal documentation 2009.

Risk management has value only when it results in action - and only when those actions clearly contribute to management’s ability to achieve their objectives. Steps in risk action management include: ? ? ? ? ? ? ? Identify the risk owner (and confirm that he or she accepts ownership) Ensure the action plan is agreed between the risk owner and the action holder Ensure the action holder understand what they have to do and by when Make sure there is some form of action tracking in place Ensure that action status is periodically reviewed Use all types of action plan as appropriate - take, transfer, terminate or treat and Make sure the risk gets closed before the risk event

There are 4 ways to act on and mitigate a risk: take (Accept the risk), transfer (Pay someone else to take the risk), treat (Prevent the risk from occurring and reduce the impact if it occurs) or terminate (Avoid the risk by adopting an alternate strategy) The mitigation plan may contain 3 types of actions: (a) Preventive actions, which are undertaken to eliminate a potential risk (reduce the probability of occurrence). (b) Contingency actions, which are
ID341.9

ICIEOM 2012 - Guimar?es, Portugal

undertaken to reduce the impact of a risk. (c) Detection actions, which are undertaken to discover as soon as possible if a risk will appear. The continuously loop is essential toward solving problems. While apparently easy to understand, it is often difficult to accomplish on an on-going basis due to, distractions, loss of focus, lack of commitment, re-assigned priorities, lack of resources, etc. Is important to make sure the action plan is executed before the risk becomes the event.

5

Finals Considerations

The present study attempted to identify the concepts of risk and vulnerability, as well as to present the process of risk management in SC. Notably, the topic has gained relevance in the academy, because it consists of a current problem in terms of supply chains. It is perceived that dealing with risk management at the enterprise level is different from treating risk, specifically in the supply chain. On the other hand, the practice in supply chain management also requires new attitudes of practitioners such as: (a) considering that risks of the company may not be the same as those on SC, (b) the shared management of risks goes by sharing information on SC, (c) understand the SCRM as a process, (d) mitigation strategies must be developed to the SC level and (e) enhance demand, suppliers and information management capabilities in the company and in the SC. Therefore, the implementation of risk management, would enable an organization, for example: Encourage proactive management; Being aware of the need to identify and address risks throughout the organization, improving the identification of opportunities and threats; Improve stakeholder confidence, establish a reliable basis for decision making, control and planning; allocate and use resources efficiently for the treatment of risks; improve operational effectiveness and efficiency; improve performance in health and safety, as well as environment protection; improve loss prevention and incidents management and minimize losses.

References
ABNT/CEE-63 (2009). ISO 63:000.01-001:Gest?o de riscos – Princípios e diretrizes. AON CORPORAION (2009). Global Risk Management Survey. CHOPRA and SODHI (2004). Managing Risks to avoid Supply Chain breakdown. MIT Sloan management Review, v.46, no.1. CHOPRA, S.; MEINDL, P.(2003). Gerenciamento da cadeia de suprimentos: estratégia, planejamento e opera??es. S?o Paulo: Pearson Prentice Hall. CHRISTOPHER, M.; MENA, C.; KHAN, O.; YURT, O. (2011). Approaches to managing global sourcing risk. Supply Chain Management: An International Journal. v. 16, n. 2, p. 67–81. CHRISTOPHER, M.G. (2009). Logística e gerenciamento da cadeia de suprimentos: criando redes que agregam valor. 2.ed. Cengage Learning. CHRISTOPHER, M.G.; MCKINNON, A.; SHARP, J.; WILDING, R.; PECK, H.; CHAPMAN, P.; J?TTNER, U.; BOLUMOLE, V. (2002). Supply chain vulnerability. Report for Department of Transport, Local Government and the Regions, Cranfield University, Cranfield. COUSINS, P.D. and SPEKMAN, R. (2003) Strategic supply and the management of inter- and intra-organisational relationships”, Journal of Purchasing & Supply Management, Vol. 9, No. 1, p. 19-29. FAISAL, M. N. BANWET, D. K. and SHANKAR, R. (2006) Supply chain risk mitigation: modeling the enablers, Business Process Management Journal, v. 12, n. 4, p. 535-552. FINCH, P (2004). Supply chain risk management, Supply Chain Management: An International Journal, Vol. 9 No. 2, pp. 183-96. J?TTNER, U. (2005). Supply chain risk management. The International Journal of Logistics Management, v. 16, n. 1, p. 120-141. J?TTNER, U.; PECK, E.; CHRISTOPHER, M. (2003). Supply chain risk management:outlining an agenda for future research. International Journal of Logistics: Research & Applications, v. 6, n. 4, p. 197-210. KHAN, O.; BURNES, B. (2007). Risk and supply chain management: creating a research agenda. International Journal of ID341.10

Risk management and mitigation strategies in the supply chain: A case study in the aeronautical industry.

Logistics Management, v. 18, n. 2, p. 197-216. LAVASTRE, O.; GUNASEKARAN, A.; SPALANZANI, A. (2012). Supply chain risk management in French companies. Decision Support Systems, v. 52, n. 4, p. 828-838. PRATER, E.; BIEHL, M.; SMITH, M. A. (2001). International supply chain agility-Tradeoffs between flexibility and uncertainty. International Journal of Operations & Production Management, v. 21, n. 5/6, p. 823-839. SPEKMAN, R.E., KAMAUFF, J.W., MYHR, N. (1998). An empirical investigation into supply chain management: a perspective on partnerships, Supply Chain Management, Vol.3 No.2, pp53-67.

ID341.11


相关文章:
...and mitigation strategies and drug safety in the US.pdf
(2014) 232238 Research Briefs Examination of risk evaluation and mitigation strategies and drug safety in the US Rosa Rodriguez-Monguio, Ph.D.a, ...
CPSM备考笔记 MOD3 Leadership in Supply Management.doc
supply chain stakeholders -internal stakeholders -...risk mitigation(缓解、减轻) -risk monitoring Task...supply management strategies should support both ...
...and Optimisation of Blast Mitigation Strategies for Design....pdf
Risk Assessment and Optimisation of Blast Mitigation Strategies for Design and Strengthening of_专业资料。维普资讯 http://www.cqvip.com Tascosoii nvri rna...
...in China: Impacts, Root Causes and Mitigation Strategies_....pdf
Desertification and Dust Storms in China: Impacts, Root Causes and Mitigation Strategies_农学_农林牧渔_专业资料。维普资讯 http://www.cqvip.com 厂: 、f/...
Supply Chain Risk Management.pdf
Supply Chain Risk Management_经管营销_专业资料。供应链风险管理 ...At Intel, three risk mitigation strategies were considered to deal with the...
...CO2-CAPTURE AS PART OF A GERMAN MITIGATION STRATEGY.pdf
Supply Under the Conditions of Globalization and Deregulation", this is by ...THE ROLE OF CCS WITHIN THE FRAMEWORK OF CO2 MITIGATION STRATEGIES In order...
...Radio Frequency Interference Mitigation Strategy for the ....pdf
ABSTRACT A Radio Frequency Interference Mitigation Strategy for the Allen Telescope Array_专业资料。We describe a multi-layered strategy for the mitigation of...
业务应变能力管理之供应链风险管理_图文.pdf
risk management (as cited by the Supply Chain Executives) Lack of ...RISK CONSULTING 20 Risk Mitigation Strategies Deriving Risk-adjusted Solutions ...
SCM World 2012首席供应链官报告(李效良等).pdf
THE CHIEF SUPPLY CHAIN OFFICER REPORT 2012 25 Section 4: Risk Management ...Management and mitigation strategies rely on communication and planning in ...
Supply-Chain-Management-04.pdf
Supply Chain Management Session 04 Slide 20 Risk Management in ...mitigation strategies: Decrease the probability of disruptions Alternative...
A Risk-based Remedy for Pharma Supply Chain Securit....pdf
risk management in suppl... 13页 5财富值 Supply Chain Risk Manage... ... and the need for end-to-end risk mitigation strategies in the industry ...
DrGodden on Enterprise Risk Management for Auto Supply ....pdf
risks Risk mitigation Risk limits Risks with no ...Generate strategies for business continuity planning ...Supply Chain/Logistics Operations ? Procurement / ...
2008PMBOK 风险-20题.pdf
There are a number of risk management tools and approaches you have been ...A.Ensure risks have been identified and mitigation strategies have been ...
可持续供应链商业案例.pdf
supply chain sustainability efforts, risk mitigation activities may include ...Conversely, reactive risk management, or contingency strategies, typically focus...
采购与供应 PART2.doc
hedging strategies to reduce exchange rate risks. ...in the supply chain is to assist in the ...vulnerability mitigation and management of capacity....
What makes a great Risk Manager 如何成为一名卓越的风险经理_....pdf
risks and propose mitigation strategies to enable ...Surprisingly in the context of risk management ... supply chain risk management, business continuity,...
Practice Questions for Risk.doc
Include assembly of certain stakeholders to identify risks and develop mitigation strategies d. Focus on those risks that senior management finds most critical...
商业银行风险管理操作及相关体系培训课件_图文.ppt
Risk Management Practices and Related Systems 风险管理操作及相关体系 Federal ...Framework - a set of integrated processes, tools and mitigation strategies ...
Risk Analysis of the International Construction Project.doc
s business risks. This will increase the probability of risk mitigation, ...Recommended key construction and risk management strategies for future ...